7 Buildings × 4 Floors × 80 Rooms. Pile Cutting to Roof handover. Steel Deck MD-75 composite floor system. Galvalume AZ150 deep-rib roof. Thai Engineering License ภย 59410.
See Manpower section for the economic proof that 10M beats 12M on cost, schedule, and competitive positioning.
Source: ENTEC Construction / SMK Holding drawings. Building: 38,500×13,500mm. 20 rooms/floor (10 per side, A+B). 4 floors = 80 rooms/building. All 7 buildings identical size.
Like editing DNA base pairs — change Schedule, Cash Flow, Risk, or Acceleration. The S-Curve recalculates and animates live. SPI, CPI, EAC update instantly.
Verified analysis: same total labor (449 man-months each). But 10M saves ฿4.07M total through slab cost, overhead reduction, and LD protection.
8 risks identified and mitigated. Schedule float analysed. Cost contingency layered with 5 protection levels. China interface protocol defined.
All-in engineering and construction excl. VAT 7%. Pile cutting to roof handover. 10M schedule committed.
License active. Team assigned. 10M committed. Contact Forma Corporations.